Minimizing the total weighted completion time in the relocation problem

Loading...
Thumbnail Image

Journal Title

Journal ISSN

Volume Title

Publisher

DOI

10.1007/s10951-009-0151-7

Abstract

This paper studies the minimization of total weighted completion time in the relocation problem on a single machine. The relocation problem, formulated from an area redevelopment project, can be treated as a resource-constrained scheduling problem. In this paper, we show four special cases to be NP-hard in the strong sense. Problem equivalence between the unit-weighted case and the UET (unit-execution-time) case is established. For two further restricted special cases, we present a polynomial time approximation algorithm and show its performance ratio to be 2.