ESTABLISHING ENGINEERING S-CURVES TO EVALUATE SUPERVISION ENGINEER ALLOCATIONS FOR HIGHWAY CONSTRUCTION PROJECTS

Loading...
Thumbnail Image

Date

Journal Title

Journal ISSN

Volume Title

Publisher

DOI

10.3846/13923730.2014.928363

Abstract

An engineering consultant firm needs to allocate engineers to supervise a highway construction project in each month during the construction phase. Properly assigning the supervision engineers under a cost-plus-fixed-fee contract has been a key factor affecting the profitability of the firm and the quality assurance of the project. Assigning too many engineers will be a waste, while allocating too few engineers may harm the supervision quality. This work proposes a two-stage model to develop engineering S-curves (called ES-curves) for planning and controlling the engineering supervision schedule. In the planning stage, a predictive ES-curve model is established based on historical ES-curves. In the controlling stage, an ES-curve is built according to the relationships between the engineering progress and construction progress. A cluster analysis and regression analysis are applied to the model development. A case study demonstrates that the produced ES-curves can help management in planning and evaluating when to increase or decrease the number of supervision engineers assigned to a project.

Description

Citation

Endorsement

Review

Supplemented By

Referenced By