Applying building information modeling to integrate schedule and cost for establishing construction progress curves
檔案
本條目沒有附加檔案。
日期
2016-12
系所
期刊名稱
AUTOMATION IN CONSTRUCTION
卷期與頁次
第 72 卷,頁 397–410
ISSN
0926-5805
語言
英文
摘要
A cost-based progress curve (called S-curve) is often used to control construction project schedules. To establish a progress curve, the costs that are associated with each scheduling activity must be determined. However, the distributions of the quantities (costs) of cost items among various activities are time-consuming to obtain and error prone, yielding an unreliable S-curve. This work proposes the use of three-dimensional building information model (BIM) objects to integrate schedule and cost by using the powerful BIM for data acquisition and storage. BIM objects are incorporated into a proposed four-step model to establish construction progress curves. The proposed model defines search criteria (cost item, object, floor, and zone) that precisely identify takeoff objects for extracting the quantities of cost items associated with each activity. The BIM uses keynote, assembly code, and family type catalog functions to provide pop-up menus for the efficient identification of cost items that are associated with each object to preventing errors in the manual typing of cost-item names. Finally, this work demonstrates that uploading the cost items and unit prices into cost estimation software in advance is critical to automating cost estimations in BIM. (C) 2016 Elsevier B.V. All rights reserved.
所屬典藏
期刊論文引用此條目
Wang, K.-C., Wang, W.-C., Wang, H.-H., Hsu, P.-Y., Wu, W.-H., & Kung, C.-J. (2016). Applying building information modeling to integrate schedule and cost for establishing construction progress curves. AUTOMATION IN CONSTRUCTION, 72, 397–410. https://doi.org/10.1016/j.autcon.2016.10.005
引用文字依 APA 第 7 版格式自動產生,使用前請再核對。
分享
永久網址:https://ir.lib.nycu.edu.tw/handle/11536/132973