An Empirical Study of Schedule Delay Causes Based on Taiwan's Litigation Cases
檔案
本條目沒有附加檔案。
日期
2013-06-01
類型
系所
期刊名稱
PROJECT MANAGEMENT JOURNAL
卷期與頁次
第 44 卷第 3 期,頁 21–31
ISSN
8756-9728
語言
英文
摘要
Many uncertainties can cause construction projects to be delayed, resulting in conflicts between the two parties to a construction contract. Using case study and content analysis methodologies, this study analyzed 79 litigation cases in Taiwan to identify the main causes of schedule delays in construction projects, which are change orders, changed scope of the work, delayed site handover, and weather. In this study, these causes are organized into a causation model to provide a reference for preventing schedule delay. The employed approach can be implemented for assessments of other regions, as schedule delays are common features in most construction projects.
所屬典藏
期刊論文引用此條目
Yang, J.-B., Chu, M.-Y., & Huang, K.-M. (2013). An Empirical Study of Schedule Delay Causes Based on Taiwan's Litigation Cases. PROJECT MANAGEMENT JOURNAL, 44(3), 21–31. https://doi.org/10.1002/pmj.21337
引用文字依 APA 第 7 版格式自動產生,使用前請再核對。
分享
永久網址:https://ir.lib.nycu.edu.tw/handle/11536/22039