ESTABLISHING ENGINEERING S-CURVES TO EVALUATE SUPERVISION ENGINEER ALLOCATIONS FOR HIGHWAY CONSTRUCTION PROJECTS
檔案
本條目沒有附加檔案。
日期
2016
系所
期刊名稱
JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT
卷期與頁次
第 22 卷第 7 期,頁 890–902
ISSN
1392-3730
語言
英文
摘要
An engineering consultant firm needs to allocate engineers to supervise a highway construction project in each month during the construction phase. Properly assigning the supervision engineers under a cost-plus-fixed-fee contract has been a key factor affecting the profitability of the firm and the quality assurance of the project. Assigning too many engineers will be a waste, while allocating too few engineers may harm the supervision quality. This work proposes a two-stage model to develop engineering S-curves (called ES-curves) for planning and controlling the engineering supervision schedule. In the planning stage, a predictive ES-curve model is established based on historical ES-curves. In the controlling stage, an ES-curve is built according to the relationships between the engineering progress and construction progress. A cluster analysis and regression analysis are applied to the model development. A case study demonstrates that the produced ES-curves can help management in planning and evaluating when to increase or decrease the number of supervision engineers assigned to a project.
關鍵詞
S-curvesupervision engineersresource allocation managementengineering consultant firmscluster analysisregression analysis所屬典藏
期刊論文引用此條目
Wang, S.-H., Wang, W.-C., Hsu, P.-Y., Chen, C.-H., & Wang, K.-C. (2016). ESTABLISHING ENGINEERING S-CURVES TO EVALUATE SUPERVISION ENGINEER ALLOCATIONS FOR HIGHWAY CONSTRUCTION PROJECTS. JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 22(7), 890–902. https://doi.org/10.3846/13923730.2014.928363