Title: Lessons from a failure case of an excavated floodway supported by precast cantilever pile walls
Authors: Cheng, Meng-Hsiung
Huang, Ming-Wan
Pan, Yii-Wen
Liao, Jyh-Jong
土木工程學系
環境工程研究所
Department of Civil Engineering
Institute of Environmental Engineering
Keywords: Floodway;Precast cantilever pile walls;Failure mechanism;Slope stability
Issue Date: 15-Jul-2016
Abstract: The Gangweigou floodway, across the Quiren and Rende districts in Tainan, Taiwan, was designed to bypass partial discharge in the Gangweigou River during heavy rainfall events for the purpose of flood control. This flood way was an excavated open channel supported by single or double rows of precast RC cantilever pile walls on each side of its banks; these piles were installed by the jetting-assisted method. Twenty days after the completion of the floodway, it was put to work for the first time during a heavy rainfall. Unexpectedly, the cantilever pile walls in several sections failed and caused the collapse of the slope behind the walls. This paper explores the failure mechanism and the real causes of failure in this case. Based on the conditions of hydrology and hydraulics, failure processes and the results of stability analyses, it was concluded that ignoring a possible bed incision or bank erosion was likely the primary problem with the improper design. The most critical condition was when the water level in the floodway quickly dropped, which resulted in rapid drawdown. The failure of the case could have been avoided if both the rapid drawdown condition and the potential of the channel bed incision were considered. (C) 2016 Elsevier B.V. All rights reserved.
URI: http://dx.doi.org/10.1016/j.enggeo.2016.05.014
http://hdl.handle.net/11536/133877
ISSN: 0013-7952
DOI: 10.1016/j.enggeo.2016.05.014
Journal: ENGINEERING GEOLOGY
Volume: 209
Begin Page: 106
End Page: 118
Appears in Collections:Articles