標題: An Empirical Study of Schedule Delay Causes Based on Taiwan's Litigation Cases
作者: Yang, Jyh-Bin
Chu, Mei-Yi
Huang, Kuei-Mei
土木工程學系
Department of Civil Engineering
關鍵字: construction projects;litigation;construction dispute;delay analysis;change orders
公開日期: 1-Jun-2013
摘要: Many uncertainties can cause construction projects to be delayed, resulting in conflicts between the two parties to a construction contract. Using case study and content analysis methodologies, this study analyzed 79 litigation cases in Taiwan to identify the main causes of schedule delays in construction projects, which are change orders, changed scope of the work, delayed site handover, and weather. In this study, these causes are organized into a causation model to provide a reference for preventing schedule delay. The employed approach can be implemented for assessments of other regions, as schedule delays are common features in most construction projects.
URI: http://dx.doi.org/10.1002/pmj.21337
http://hdl.handle.net/11536/22039
ISSN: 8756-9728
DOI: 10.1002/pmj.21337
期刊: PROJECT MANAGEMENT JOURNAL
Volume: 44
Issue: 3
起始頁: 21
結束頁: 31
Appears in Collections:Articles