On relocation problems with multiple identical working crews

Loading...
Thumbnail Image

Journal Title

Journal ISSN

Volume Title

Publisher

DOI

10.1016/j.disopt.2006.06.003

Abstract

The relocation problem was formulated from a public housing project. In its basic form, a set of buildings needed to be torn down and erected by a single working crew. Given a fixed budget, the relocation problem seeks to determine a feasible reconstruction sequence of the old buildings. This problem has been shown to be mathematically equivalent to the classical two-machine flowshop of makespan minimization. In this paper, we consider a variant where multiple working crews are available for the redevelopment project. Most of our results center on the situations where all buildings require the same redevelopment time. We first present a strong NP-hardness proof for the case with two working crews. Then, we give a negative result about the approximability of the studied problem. Approximation algorithms and associated performance-ratio analysis are designed for the cases with unbounded as well as bounded numbers of machines. (c) 2006 Elsevier B.V. All rights reserved.

Description

Citation

Endorsement

Review

Supplemented By

Referenced By