标题: 关键链专案管理执行计划之研究
The Implementation Plan of Critical Chain Project Management
作者: 张玉旻
Yu-Min Chang
李荣贵
Rong-kwei Li
管理学院工业工程与管理学程
关键字: 关键链专案管理;策略与战术图;限制理论;Critical Chain Project Management;Strategy and Tactic Tree;TOC
公开日期: 2006
摘要: 关键链专案管理(Critical Chain Project Management, CCPM)是1997年由Eliyahu M. Goldratt所提出的限制理论(Theory of Constraints, TOC)管理方法之一。Goldratt延续其限制理论的主张,认为专案环境中,唯有专案如期达交才能使企业获得产出(throughput)而达到良好的绩效表现。因此,造成专案无法如期达交而绩效不佳的限制因素,便是专案环境的瓶颈。由于专案是由一系列的相依任务和资源所组成,因此专案交期受到任务相依和资源相依的最长路径─关键链─的影响,故由关键链长度所决定的专案时程便是专案管理的瓶颈,即企业改善专案管理绩效的杠杆点。
近十年来,关键链专案管理所阐扬的管理思维在实绩的佐证下,已陆续证实其有效性。然而,现有相关研究偏重关键链排程及缓冲管理之技术议题探讨、针对关键链持正反两方的辩论、或关键链与要径法的比较,对于如何执行甚少着墨。
2006年Goldratt提出策略与战术图,将其概念层层展开,发展为架构更明确的改善方案,其中针对专案交期绩效的改善提出了六个改善方案。不过,由于此六个改善方案仍属于较高层次的中继目标,距企业实际导入时赖以依循的步骤仍有差距,本研究以策略与战术图为主轴,进一步发展与研究出适用于导入的执行任务和执行计画,让有意导入关键链专案管理的企业有参考的依据。
Critical Chain Project Management is one of the applications of TOC (Theory of Constraints) proposed by Eliyahu M. Goldratt in 1997. Continuing his assertion, Goldratt claims enterprises can gain throughputs and achieve good performance only when they can deliver projects on time for project environments. Therefore, the restricted factor causing projects delay is the constraint of project environments. Projects are composed of series of tasks and resources. Accordingly, the project due date is affected by the longest path, called “Critical Chain”, composed of dependent tasks and resources. The project schedule determined by the length of Critical Chain is consequently the constraint of project management which is the leverage point for enterprises to improve their project performances.
In this decade, CCPM has proved its practicality by increasing successful implementations. However, the tendencies of present researches are technical issues of critical chain scheduling and buffer calculations, debates between supporters and antagonists, and comparisons between CCPM and CPM (Critical Path Management). There are seldom discussions about execution of CCPM.
In 2006, Goldratt proposed “Strategy and Tactic Tree (S&T Tree)” to deploy his concepts into executable scheme. There are six sub-topics regarding high project due date performance. The author considers these six sub-topics are intermediate objectives which deserves further studies. This thesis deploys executable tasks and constructs the implementation plan based on S&T Tree for those who feel interested.